W O C S
Worldwide Optical Câble Services
Part 1 :
Table of contents
1 / INTRODUCTION
2 / EXAMPLE OF CIVIL WORKS FOR LANDING STATION
3 / EXAMPLE OF SUBDUCTING &PULLING OF CABLES
4 / OGB : SUPPLY & INSTALLATION ELECTRODES & EARTH PLATE
1 / INTRODUCTION
That document is to show some examples of our works done from many years for the land part installation – shore-end works & laying of optical submarine cable projects.
2 / EXAMPLE OF CIVIL WORKS FOR LANDING STATION
Project ORASCOM – ORAN :
Excavation of the site and starting construction of the retaining wall basement
Installation of the shelters
Site completed
Excavation of the site and starting construction of the retaining wall basement
Installation of the shelters
Site completed
3 / Example of subducting & pulling of cables
Project IMEWE – JEDDAH :
Supply and installation of Subduct (50 + 40)
Preparation for cable pulling
Fixation of cable grip
3 / Example of subducting & pulling of cables
Project IMEWE – JEDDAH :
Supply and installation of Subduct (50 + 40)
Preparation for cable pulling
Fixation of cable grip
Project SMW 3 – Macau :
Example of 8 digits for cable pulling
Project SMW 3 – Macau :
Example of 8 digits for cable pulling
4 / OGB :
Supply & installation electrodes
4 / OGB :
Project SMW 3 – macau :
Project SMW 3 – macau :
Installation Sea earth plate & Articulated Pipe on the beach
Beach trench & pulling earth plate cable inside the beach manhole
Project SMW 3 – macau :
Installation Sea earth plate & Articulated Pipe on the beach
Beach trench & pulling earth plate cable inside the beach manhole
Part 2 :
Table of contents
5 / CIVIL WORKS FOR DUCT ROUTE CONSTRUCTION
6 / EXEMPLE OF LANDDING OPERATION & SUB-RIVER WORKS
6 / CONCLUSION
5 / Civil works for duct route construction
Project ORASCOM – Oran :
Construction of Beach Manhole
Construction of Beach Manhole
Construction of Beach Manhole End of seaward ducts
5 / Civil works for duct route construction
Project ORASCOM – Oran :
Construction of Beach Manhole
Project TE North – Abu Talat
EGYPTE :
Construction of a beach manhole cover End of pipes to the sea
Lay out seaward ducts
Construction of the duct route
Project TE North – Abu Talat
EGYPTE :
Construction of a beach manhole cover End of pipes to the sea
Lay out seaward ducts
Construction of the duct route
Project TE North – Marseille
France :
Construction of the duct route Installation of the HDD equipment
Preparation of HDPE pipes Soldering the 2 half segment of HDPE pipes
Pulling of FO cable
Put in place the perfabricated Beach Manhole
Project TE North – Marseille
France :
Construction of the duct route Installation of the HDD equipment
Start of the drilling
Preparation of HDPE pipes Soldering the 2 half segment of HDPE pipes
Subducting HDPE pipes
Pulling of FO cable
Put in place the perfabricated Beach Manhole
Installation of shelters for the landing station
Project Orascom – Oran :
Landing operation – Starting of pulling submarine cable
Recuperation of the cable
Installation of Articulated Pipes – End of seaward ducts
Project Orascom – Oran :
Landing operation – Starting of pulling submarine cable
Anchoring the S / M cable in BMH
Beach seal
Project ST LOUIS / SENEGAL :
Loading the cable on the modular pontoon
Protection of the submarine cable with articulated cast iron pipes manufactured and supplied by WOCS
6 / Landing operation & subriver works
Project Cross River Gambia :
Preparation of the barage
Localisation of the faults at the Beach Manhole
Recuperation of the cable cut
Jointing reparation on the barge
7 / Conclusion
Following our experience, we can take in charge all the operations for the installation of the land part of submarine cable projects Or Backhaul cable :
- Survey & Engineering for the coonstruction of duct route -landing station & network telecom link.
- Study of the system earth (Ocean Ground Bed – OGB) : Resistivity measurement – soil study.
- Supply Qualified jointing boxes for submarine or terrestril optical cable – earth or power cable Supply Electrodes & Installation.
- Management of local contractor.
- Installation and Jointing FO cables & copper cables Boxes.
- Acceptance tests : All tests and controls to be performed on optical and copper land cables used at the land part of a submarine link or backhaul cable.
- Shore-end works – Landing operations & Laying of sub-river cable, including supply & installation articulated pipes – burial by jeting up to 20 m water depth – video reporting.
- Training Course.
- Maintenance of existing link.